Apprentices complete a required number of hours in on-the-job training and related instruction.
Journey Electrician
Anonymous
National (OA)
Documents
Coming Soon
Individual state requirements may vary. Please contact your local apprenticeship office to ensure this version is suitable to your state’s requirements.
Work Process Content
On the Job Training
Anonymous
Hours do not meet minimum OA standard for this occupation
7.6K
OJT hours
CONNECTING, TESTING, GROUNDING TRANSFORMER, SERVICE WIRES, METERS & STREETLIGHTS
0
1.4K
RIGGING
0
200
WIRE (STRINGING, SAGGING, JOINING)
0
500
TRANSMISSION LINES and TOWERS
0
400
MATERIAL HANDLING and INVENTORY
0
300
SUBSTATION STRUCTURES and EQUIPMENT
0
400
CONTROL WIRING and TROUBLESHOOTING
0
1K
PROTECTION and CONTROL EQUIPMENT
0
700
LIVE BUSS MAINTENANCE, TESTING and CONSTRUCTION
0
1.1K
OPERATING EQUIPMENT (SKIDSTEER, MINI-X, TRENCHER)
0
800
JOB SITE SAFETY and OTHER WORK
0
800
Related Instruction Content
Training Provider(s):
Huntsville Utilities
580
RI hours
Climbing Wood Poles
Basic Electricity
A/C Fundamental
Electrical Safety
56
Intro to T&D Systems
Transmission
Distribution
Safety in T&D Maintenance
Substations & Switchyard
48
Using Tools Bucket Trucks 1
Bucket Trucks 2
Rigging 1
40
Power Transformers 1 Intro to Metering
Safety in Meter Work
Safety in Substation/Switchyards
Circuit Breakers 1 Voltage Regulators 1
36
Safety in Overhead Line Maintenance Safe Bucket Truck Operation
Bucket Truck Rescue
Rigging 2
24
Service Installations
Overhead Distribution Systems
Map Reading Basic Substation Switching (Transferring & Bypassing)
URD Systems
Pad Mounted Transformers & Switchgear
Transformer Connection
Pole Top Equipment & Replace (Transformers)
Transformer Trouble Shooting
38
Working on Distribution Poles
Advanced Rigging
24
Power Quality
Substation Print Reading
Intermediate Substation Switching (Swapping Zones)
48
Multi-meter Operation
Care & Testing of Tools & Equipment
Battery Maintenance & Testing
Oil Testing
TVPPA (Substation Maintenance II)
34
Control Equipment
Equipment Print Reading
18
Power Transformers 2 Transformer Testing
Circuit Breakers 2
Breaker Testing
38
Pole Top Equipment & Replace (Voltage Regulators)
Capacitors & Reactors
Pole Top Equipment & Replacement (Capacitors)
Voltage Regulators 2
Regulator Testing